Construction Updates
Shipp Chapel & Concourse Addition & Renovation
30 Day Construction Forecast Schedule
November 2-6, 2009
  • On-going interior painting in Area A&B and Shipp Chapel.
  • On-going Mechanical and Electrical Fixture Trim-out in Area A&B and Shipp.
  • On-going installation of Tile flooring in Shipp Chapel.
  • On-going installation of Millwork & Wood Paneling in Area A&B.
  • On-going installation of exterior building caulking.
  • On-going installation of sidewalks, pavers, and landscaping.
  • On-going tape, bed, and paint of 2nd Floor Administration Area
November 9-13, 2009
  • On-going interior painting in Area A&B and Shipp Chapel.
  • On-going Mechanical and Electrical Fixture Trim-out in Area A&B and Shipp.
  • On-going installation of Tile flooring in Shipp Chapel.
  • On-going installation of Millwork & Wood Paneling in Area A&B.
  • On-going installation of exterior building caulking.
  • On-going installation of sidewalks, pavers, and landscaping.
  • On-going tape, bed, and paint of 2nd Floor Administration Area.
  • Begin installation of A/V & Theatrical Lighting System in Shipp Chapel.
  • Begin installation of Site Lighting.Installation of pews in Shipp Chapel.
  • Installation of Pendant Light Fixtures in Shipp Chapel.
November 16-20, 2009
  • On-going interior paint touch-up in Area A&B and Shipp Chapel.
  • On-going Mechanical and Electrical Fixture Trim-out in Area A&B and Shipp.
  • On-going installation of Tile flooring in Shipp Chapel and Area A&B.
  • On-going installation of Millwork & Wood Paneling in Area A&B and Shipp.
  • On-going installation of exterior building caulking.
  • On-going installation of pavers, and landscaping.
  • On-going paint touch-up of 2nd Floor Administration Area.
  • On-going installation of A/V & Theatrical Lighting System in Shipp Chapel.
  • On-going installation of Site Lighting.Begin installation of metal handrails.
  • Begin installation of flooring in 2nd Floor Administration Area.
  • Begin Mechanical, Electrical, & Plumbing Final Inspections.
November 23-27 & 30, 2009
  • On-going interior paint touch-up in Area A&B and Shipp Chapel.
  • On-going installation of Millwork & Wood Paneling in Area A&B and Shipp.
  • On-going installation of exterior building caulking.
  • On-going installation of pavers, and landscaping.
  • On-going paint touch-up of 2nd Floor Administration Area.
  • On-going installation of A/V & Theatrical Lighting System in Shipp Chapel.
  • On-going installation of Site Lighting.On-going installation of metal handrails.
  • On-going installation of flooring in 2nd Floor Administration Area.
  • Begin Final Inspections with City of Dallas.