| Day 1: Oct. 13 |
Priority 1 |
Priority 2 |
| |
Stand walls |
Put up Porch Beams |
| |
Brace, string, rebrace walls |
|
| |
Run Cap Plate |
Blue Board or Felt Walls |
| |
Mark truss layout |
|
| |
Brick Flashing |
|
| |
Sheath walls |
|
| |
Load Trusses |
|
| |
Stand Trusses |
Install Porch Posts |
| |
Install K-Braces |
Blue Board or Felt Walls |
| Day 2: Oct. 20 |
Install Z and X bracing |
Rat runs/ Mid-Wed runs |
| |
Install Lookout ladders |
Hurricane ties |
| |
Run Sub-Fascia |
|
| |
ADA blocking behind tub |
Insulate behind Tub |
| |
Be deck ready |
|
| |
Deck roof/ Felt roof |
Rat runs / Mid web runs |
| |
Fascia |
Hurricane ties |
| Day 3: Oct. 27 |
Drip Edge |
Blue Board or Felt Gables |
| |
Sheath Gables |
ADA blocking / deadwood |
| |
Install Windows |
Cut out thresholds |
| |
Install Ext. Doors |
Attic access |
| |
Dried In |
|
| |
Run Shingles |
Start Siding |
| |
Start Ext. Trim: |
Trim out Porch |
| Day 4: Nov. 3 |
Soffit |
Brick Frieze |
| |
Siding Prep |
|
| |
|
|
| |
Shingles 80% Complete |
|
| |
Finish Shingles |
|
| |
Ridge Vent and Cap |
|
| Day 5: Nov. 10 |
Finish Soffit |
|
| |
Brick Frieze |
|
| |
Siding |
|
| |
Siding Trim |
|
| |
Finish Roof |
|
| |
Finish Siding |
|
| |
Finish Trim |
|
| Day 6: Nov. 17 |
Exterior Paint Prep |
|
| |
Be Paint Ready |
|
| |
Finish all Paint prep |
Rough grade lot by hand if
necessary |
| |
Finish all remaining trim |
|
| Day 7: Dec. 1 |
Paint house |
|
| |
2 coats of Paint Done |
|
| |
Smooth lot by hand if
necessary |
Finish Punch Items |
| |
Lay sod |
|
| Day 8: Dec. 8 |
Plant trees |
|
| |
Plant shrubs, flowers |
|
| |
Exterior of house complete |
|
| |
DEDICATION |
|
|