Habitat for Humanity Build Information - 2007
To download PDF with additional details and release form, click here.
Build Schedule
Day 1: Oct. 13 Priority 1 Priority 2
  Stand walls Put up Porch Beams
  Brace, string, rebrace walls  
  Run Cap Plate Blue Board or Felt Walls
  Mark truss layout  
  Brick Flashing  
  Sheath walls  
  Load Trusses  
  Stand Trusses Install Porch Posts
  Install K-Braces Blue Board or Felt Walls
Day 2: Oct. 20 Install Z and X bracing Rat runs/ Mid-Wed runs
  Install Lookout ladders Hurricane ties
  Run Sub-Fascia  
 

ADA blocking behind tub

Insulate behind Tub
  Be deck ready  
  Deck roof/ Felt roof Rat runs / Mid web runs
  Fascia Hurricane ties
Day 3: Oct. 27 Drip Edge Blue Board or Felt Gables
  Sheath Gables

ADA blocking / deadwood

  Install Windows Cut out thresholds
  Install Ext. Doors Attic access
  Dried In  
  Run Shingles Start Siding
  Start Ext. Trim: Trim out Porch
Day 4: Nov. 3

Soffit

Brick Frieze
  Siding Prep  
     
  Shingles 80% Complete  
  Finish Shingles  
  Ridge Vent and Cap  
Day 5: Nov. 10 Finish Soffit  
  Brick Frieze  
  Siding  
  Siding Trim  
  Finish Roof  
  Finish Siding  
  Finish Trim  
Day 6: Nov. 17 Exterior Paint Prep  
  Be Paint Ready  
  Finish all Paint prep Rough grade lot by hand if necessary
  Finish all remaining trim  
Day 7: Dec. 1 Paint house  
  2 coats of Paint Done  
  Smooth lot by hand if necessary Finish Punch Items
  Lay sod  
Day 8: Dec. 8 Plant trees  
  Plant shrubs, flowers  
  Exterior of house complete  
  DEDICATION  